May 22, 2016
Chris gives a final cascade of snow to the staircase balloon.
The weather continues to be cooperative, and today was a really good day for blowing back the trenches.
We are getting into the routine, and all balloons behaved as expected. There was a really funny aspect to the installation of a vent pipe right over the centre of the drill trench. Malte had to climb the inflated balloon and hold the vent pipe in position while it was tethered at the sides of the excavation. After a job well done, it turned out that the lid for the pipe had been forgotten, so Malte was suspended from the crane waring a body harness to put the lid on. After that, the backfilling of the trenches was relatively uneventful, while the balloon pressures were carefully maintained and monitored from the science trench. Now we have to wait three days to behold the results.
What we have done today:
Ad. 1 and 2: The elevator is now safe to use, and the railing around the elevator hole on the surface prevents people from falling 6 m down.
Weather today: Clear all day. Temp. -15°C to -25°C, Wind 8 kt from SW. Visibility: To horizon. Beautiful day.
FL, J.P. Steffensen
The balloons are lined up before inflation.
A proud construction manager poses in front of the big balloon.
The balloons are inflated. Here is the intersection of the ramp, drill trench and staircase shaft.
Hans Christian, Joel and Malte wait while the balloons inflate.
Christian finishes the railing around the elevator shaft.
Joel falls victim to a grand assault from the Pistenbully snow blower.
A picture from the drone while blowing snow.